Electrical Maintenance Checklist

Free electrical maintenance checklists for building power assets — HV and LV switchgear, distribution boards, standby generators, UPS, solar PV, EV charging, battery storage, and more. Each includes preventive tasks, frequencies, common faults, and safety notes.

Electrical maintenance checklist template covering thermographic surveys, RCD testing, distribution board inspections and emergency lighting tests with frequencies
A preview of the electrical maintenance checklist format — every checklist is free to download as a PDF.

Electrical maintenance combines visual inspection, thermographic and connection checks, functional testing (generators, ATS, UPS), and statutory inspection such as the periodic EICR. Only competent electrical persons should carry out intrusive work. Choose the checklist for your specific asset below.

Other maintenance checklist categories

HVAC maintenance checklistsAir handling units, fan coils, chillers, VRF, ductwork and extract systems — filters, coils, refrigerant and damper checks.
heating maintenance checklistsBoilers, calorifiers, heat exchangers, heat pumps and flues — combustion, controls and hot water safety checks.
plumbing and water system maintenance checklistsPressurisation units, booster sets, storage tanks, TMVs and water treatment — pressure, hygiene and legionella control.
fire safety maintenance checklistsFire dampers, alarms, emergency lighting, sprinklers, risers and fire doors — the statutory checks and their records.
BMS and controls maintenance checklistsBMS panels and head-ends, DDC controllers, inverters, sensors and actuators — calibration, overrides and strategy backups.
metering maintenance checklistsEnergy, heat, water and gas meters — read integrity, accuracy checks and the data quality behind aM&T reporting.
lift maintenance checklistsPassenger, goods and platform lifts and escalators — LOLER thorough examination, entrapment release and door safety.

The EICR cycle and what sits around it

For commercial premises the fixed wiring is inspected via an Electrical Installation Condition Report, typically on a five-year cycle (shorter for industrial environments, swimming pools, or where the previous report recommends it). The EICR is a snapshot, not a maintenance regime — the C1/C2 observations it raises still need remedial work, and everything between inspections relies on routine maintenance: thermographic surveys to catch hot joints before they fail, torque checks on terminations, RCD test-button checks, and keeping boards clear, labelled, and covered.

Duty holders under the Electricity at Work Regulations 1989 must maintain electrical systems so far as reasonably practicable to prevent danger. In practice that means a documented preventive schedule plus records — service sheets, thermography reports, and the EICR itself — that together demonstrate the installation is being managed.

Standby power needs testing, not just servicing

Generators, UPS systems, and automatic transfer switches fail quietly: the battery that won't crank, the changeover that sticks, the UPS bank past its design life. A weekly or monthly off-load run proves the generator starts; an annual on-load or building black-start test proves the whole chain works, including the transfer switch and essential-services boards. UPS batteries are usually impedance-tested annually and replaced on condition or at the manufacturer's design life rather than on failure.

Log run hours, test results, and battery readings every time — trend data is what tells you a battery string is degrading before the mains event that exposes it.

Frequently asked questions

What does an electrical maintenance checklist cover?
It covers visual inspection of switchgear and boards, termination and thermographic checks for hot joints, functional testing of standby systems (generators, ATS, UPS), and asset-specific checks for solar PV, EV chargers, and battery storage. Statutory electrical inspection — the periodic Electrical Installation Condition Report (EICR) — sits alongside this preventive maintenance.
How often is electrical maintenance required?
Frequencies vary by asset: standby generators are often run weekly and load-tested annually, UPS and switchgear are serviced annually, and the fixed installation is inspected via an EICR typically every five years for commercial premises. Critical and heavily used assets may need more frequent attention.
Who can carry out electrical maintenance?
Intrusive electrical work must be carried out by competent, qualified electrical persons, and statutory inspections like the EICR require an appropriately qualified electrician. These checklists provide the framework of tasks; the work itself should always be done by competent personnel following safe isolation procedures.