R-407C GWP and CO₂e
R-32 / R-125 / R-134a blend — R-32/125/134a (23/25/52). Restricted. Largely a legacy and retrofit refrigerant; it is zeotropic, so a leak changes the remaining charge's composition and the system needs a full recharge rather than a top-up.
Great Britain
1,774
Computed per retained Regulation (EU) No 517/2014, Annex IV, from Annex I/II component values
EU / Northern Ireland
1,774
Computed per Regulation (EU) 2024/573, Annex VI, from Annex I/II component values
The figure is the same in both regimes. Both state their values on an IPCC Fourth Assessment Report basis for this substance, so a number quoted from AR5 or AR6 will not match the one that governs compliance.
How this number is arrived at
R-407C is a blend, so neither regulation lists a GWP for it directly. Both set out the same method — a mass-weighted average of the components — and both list the component values in their own annexes. The arithmetic is below so you can check it rather than take it on trust.
| Component | % by mass | GWP (GB) | GWP (EU/NI) |
|---|---|---|---|
| R-32 | 23% | 675 | 675 |
| R-125 | 25% | 3500 | 3500 |
| R-134a | 52% | 1430 | 1430 |
Great Britain: (0.23 × 675) + (0.25 × 3500) + (0.52 × 1430) = 155.25 + 875 + 743.6 = 1773.85, reported as 1774
EU / Northern Ireland: (0.23 × 675) + (0.25 × 3500) + (0.52 × 1430) = 155.25 + 875 + 743.6 = 1773.85, reported as 1774
Composition from ASHRAE Standard 34, as published in the ASHRAE Handbook—Fundamentals refrigerants chapter. Method from Regulation (EU) 2024/573 Annex VI and the retained GB Annex IV, which are worded identically.
Charge in kg → tonnes CO₂e
t CO₂e = charge (kg) × GWP ÷ 1,000. This figure, not the charge in kilograms, is what sets the statutory leak-check frequency.
| Charge | t CO₂e (GB) | t CO₂e (EU/NI) |
|---|---|---|
| 1 kg | 1.77 | 1.77 |
| 2 kg | 3.55 | 3.55 |
| 5 kg | 8.87 | 8.87 |
| 10 kg | 17.74 | 17.74 |
| 20 kg | 35.48 | 35.48 |
| 50 kg | 88.70 | 88.70 |
| 100 kg | 177.40 | 177.40 |
Leak-check thresholds in kg
The regulations set the bands in tonnes CO₂e. Converted to a charge of R-407C, the duty starts at these weights.
| Band | Charge (GB) | Charge (EU/NI) | Check at least | With leak detection |
|---|---|---|---|---|
| ≥5 t CO₂e | 2.82 kg | 2.82 kg | At least every 12 months | Every 24 months |
| ≥50 t CO₂e | 28.2 kg | 28.2 kg | At least every 6 months | Every 12 months |
| ≥500 t CO₂e | 282 kg | 282 kg | At least every 3 months | Every 6 months |
Automatic leak detection is mandatory at 500 tonnes CO₂e and above. Hermetically sealed equipment labelled as such is exempt below 10 tonnes CO₂e. Records must be kept for at least five years. Sources: retained Regulation (EU) No 517/2014 Articles 4–6, Regulation (EU) 2024/573 Articles 5–7, and GOV.UK guidance on checking F-gas equipment for leaks.
Where you meet R-407C
- •R-22 retrofit on legacy chillers and heat pumps
- •Air conditioning installed in the R-22 transition years
- •Some air-cooled chillers and close-control units